ABSTRACT
The
problem studied in this paper was inspired from an actual textile
company. The problem is more complex than usual scheduling problems in
that we compute overtime requirements and make scheduling decisions
simultaneously. Since having tardy jobs is not desirable, we allow
overtime to minimize the number of tardy jobs. The overall objective is
to maximize profits. We present various mathematical models to solve
this problem. Each mathematical model reflects different overtime
workforce hiring practices. An experimentation has been carried out
using eight different data sets from the samples of real data collected
in the above mentioned textile company. Mathematical Model 2 was the
best mathematical model with respect to both profit and execution time.
This model considered partial overtime periods and also allowed
different overtime periods on cells. We could solve problems up to 90
jobs per period. This was much more than what the mentioned textile
company had to handle on a weekly basis. As a result, these models can
be used to make these decisions in many industrial settings.
Cite this paper
References
Süer, G. and Mathur, K. (2015) Mathematical Models to Simultaneously Determine Overtime Requirements and Schedule Cells. Engineering, 7, 58-72. doi: 10.4236/eng.2015.72006.
| [1] | Suresh,
N.C. and Kay, J.M. (1998) Group Technology and Cellular Manufacturing: A
State-of-the-Art Synthesis of Research and Practice. Kluwer Academic,
Boston. http://dx.doi.org/10.1007/978-1-4615-5467-7 |
| [2] | Süer,
G.A., Saiz, M., Dagli, C. and Gonzalez, W. (1995) Manufacturing Cell
Loading Rules and Algorithms for Connected Cells. Manufacturing Research
and Technology Journal, 24, 97-127. http://dx.doi.org/10.1016/S1572-4417(06)80038-0 |
| [3] | Süer,
G.A., Saiz, M. and Gonzalez, W. (1999) Evaluation of Manufacturing Cell
Loading Rules for Independent Cells. International Journal of
Production Research, 37, 3445-3468. http://dx.doi.org/10.1080/002075499190130 |
| [4] | Süer,
G.A., Vazquez, R. and Cortes, M. (2005) A Hybrid Approach of Genetic
Algorithms and Local Optimizers in Cell Loading. Computers and
Industrial Engineering, 48, 625-641. http://dx.doi.org/10.1016/j.cie.2003.03.005 |
| [5] | Süer,
G.A., Arikan, F. and Babayigit, C. (2008) Bi-Objective Cell Loading
Problem with Non-Zero Setup Times with Fuzzy Aspiration Levels in Labour
Intensive Manufacturing Cells. International Journal of Production
Research, 46, 371-404. http://dx.doi.org/10.1080/00207540601138460 |
| [6] | Süer,
G.A., Arikan, F. and Babayigit, C. (2009) Effects of Different Fuzzy
Operators on Fuzzy Bi-Objective Cell Loading Problem in Labor-Intensive
Manufacturing Cells. Computers & Industrial Engineering, 56,
476-488. http://dx.doi.org/10.1016/j.cie.2008.02.001 |
| [7] | Süer,
G.A. and Dagli, C. (2005) Intra-Cell Manpower Transfers and Cell
Loading in Labor-Intensive Manufacturing Cells. Computers &
Industrial Engineering, 48, 643-655. http://dx.doi.org/10.1016/j.cie.2003.03.006 |
| [8] | Süer,
G.A., Cosner, J. and Patten, A. (2009) Models for Cell Loading and
Product Sequencing in Labor-Intensive Cells. Computers & Industrial
Engineering, 56, 97-105. http://dx.doi.org/10.1016/j.cie.2008.04.002 |
| [9] | Yarimoglu,
F. (2009) Cell Loading and Product Sequencing Subject to Manpower
Restrictions in Synchronized Manufacturing Cells, Ohio University. http://etd.ohiolink.edu/send-pdf.cgi/Yarimoglu%20Fatih.pdf?ohiou1234899632 |
| [10] | Nakamura, N., Yoshida, T. and Hitomi, K. (1978) Group Production Scheduling for Minimum Total Tardiness Part(I), AIIE Transactions, 10, 157-162. |
| [11] | Hitomi, K. and Ham, I. (1976) Operations Scheduling for Group Technology Applications. CIRP Annals, 25, 419-422. |
| [12] | Ham, I., Hitomi, K., Nakamura, N. and Yoshida, T. (1979) Optimal Group Scheduling and Machining-Speed Decision under Due-Date Constraints. Transactions of the ASME Journal of Engineering for Industry, 101, 128-134. |
| [13] | Pan,
J.C.H. and Wu, C.C. (1998) Single Machine Group Scheduling to Minimize
Mean Flow Time Subject to Due Date Constraints. Production Planning and
Control, 9, 366-370. http://dx.doi.org/10.1080/095372898234091 |
| [14] | Gupta,
J.N.D. and Chantaravarapan, S. (2008) Single Machine Group Scheduling
with Family Setups to Minimize Total Tardiness. International Journal of
Production Research, 46, 1707-1722. http://dx.doi.org/10.1080/00207540601009976 |
| [15] | Süer, G.A. and Mese, E.M. (2011) Cell Loading and Family Scheduling for Jobs with Individual Due Dates. In: Modrák, V. and Pandian, R.S., Eds., Operations Management Research and Cellular Manufacturing Systems: Innovative Methods and Approaches, IGI Global, Hershey, 208-226. |
| [16] | Süer, G.A., Santos, J. and Vazquez, R. (1999) Scheduling Rotary Injection Molding Machines. Proceedings of the Second Asia-Pacific Conference on Industrial Engineering and Management Systems, Kanazawa, 30-31 October 1999, 319-322. |
| [17] | Süer,
G.A., Subramanian, A. and Huang, J. (2009) Heuristic Procedures and
Mathematical Models for Cell Loading and Scheduling in a Shoe
Manufacturing Company. Computers & Industrial Engineering, 56,
462-475. http://dx.doi.org/10.1016/j.cie.2008.10.008 |
| [18] | Huang,
J., Süer, G.A. and Urs, S.B.R. (2011) Genetic Algorithm for Rotary
Machine Scheduling with Dependent Processing Times. Journal of
Intelligent Manufacturing, 23, 1931-1948. http://dx.doi.org/10.1007/s10845-011-0521-9 |
| [19] | Mathur,
K. and Süer, G.A. (2013) Math Modeling and GA Approach to
Simultaneously Make Overtime Decisions, Load Cells and Sequence
Products. Computers & Industrial Engineering, 66, 614-624. http://dx.doi.org/10.1016/j.cie.2013.08.012 |
| [20] | Maxwell, W.L. (1970) On Sequencing n Jobs on One Machine to Minimize the Number of Late Jobs. Management Science, 16, 295-297. http://dx.doi.org/10.1287/mnsc.16.5.295 |
| [21] | Süer,
G.A., Pico, F. and Santiago, A. (1997) Identical Machine Scheduling to
Minimize the Number of Tardy Jobs When Lot-Splitting Is Allowed.
Computers & Industrial Engineering, 33, 277-280. http://dx.doi.org/10.1016/S0360-8352(97)00092-2 eww150215lx |
评论
发表评论